Just a little update as things seem to be very quiet in the world of Beechwood.
On Friday 4th March I went in to the Beechwood sales office and met with Ashleigh again. Mandy had provided us with the plans and advised us to make any changes necessary and return them. We looked at a few minor cosmetic changes, nothing structural but it was then that Ashleigh informed me that the we could do this at colour selection. So it seemed a week wasted when all we had to do was sign off on the buildings' overall plan/footprint. Those changes that we made were then added and sent off to the drafting team.
Its now been almost 2 weeks and we have heard nothing back. 1 week wasted has now become 3 weeks wasted.
Still, on the plus side of that, the land hasn't been registered so there is technically nowhere to build yet... plus we snuck in through an open gate and had a good inspection of the block!
Tuesday, 15 March 2016
Tuesday, 1 March 2016
Timeline
21.11.2015 Tender 1 received
11.12.2015 Variations submitted
15.12.2015 Tender 2 received
16.12.2015 Paid deposit on land
17.12.2015 Received Beechwood contract
17.12.2015 Paid deposit on build
18.12.2015 Sign contract
20.02.2016 Received 1st draft of plans
28.02.2016 Received 2nd draft of plans after variations
30.03.2016 Land registered through council
16.05.2015 Plan approval from council and engineers
23.05.2016 Colour Selection
24.05.2016 Variation 3 received after colours
27.05.2016 Tile section finalised and ordered
11.12.2015 Variations submitted
15.12.2015 Tender 2 received
16.12.2015 Paid deposit on land
17.12.2015 Received Beechwood contract
17.12.2015 Paid deposit on build
18.12.2015 Sign contract
20.02.2016 Received 1st draft of plans
28.02.2016 Received 2nd draft of plans after variations
30.03.2016 Land registered through council
16.05.2015 Plan approval from council and engineers
23.05.2016 Colour Selection
24.05.2016 Variation 3 received after colours
27.05.2016 Tile section finalised and ordered