Tuesday 15 March 2016

Just a little update as things seem to be very quiet in the world of Beechwood.

On Friday 4th March I went in to the Beechwood sales office and met with Ashleigh again. Mandy had provided us with the plans and advised us to make any changes necessary and return them. We looked at a few minor cosmetic changes,  nothing structural but it was then that Ashleigh informed me that the we could do this at colour selection. So it seemed a week wasted when all we had to do was sign off on the buildings' overall plan/footprint. Those changes that we made were then added and sent off to the drafting team.

Its now been almost 2 weeks and we have heard nothing back. 1 week wasted has now become 3 weeks wasted.

Still, on the plus side of that, the land hasn't been registered so there is technically nowhere to build yet... plus we snuck in through an open gate and had a good inspection of the block!

Tuesday 1 March 2016

Timeline

21.11.2015    Tender 1 received

11.12.2015    Variations submitted

15.12.2015    Tender 2 received

16.12.2015    Paid deposit on land

17.12.2015    Received Beechwood contract

17.12.2015    Paid deposit on build

18.12.2015    Sign contract

20.02.2016    Received 1st draft of plans

28.02.2016    Received 2nd draft of plans after variations

30.03.2016    Land registered through council

16.05.2015    Plan approval from council and engineers

23.05.2016    Colour Selection

24.05.2016    Variation 3 received after colours

27.05.2016    Tile section finalised and ordered